Signal and level crossing failure: Groningen-Leeuwarden (16 September 2019)
Current status:
This disruption is resolved.
-
Disruption resolved Last update
Between Groningen and Leeuwarden the train traffic is fully resumed.
- Show complete timeline…
-
Disruption reported
Between Groningen and Leeuwarden there are delays and fewer trains are running due to a signal failure.
This will take until approximately 8:30 AM hours.
Location of this disruption
This disruption is between Groningen and Leeuwarden.
More about this disruption
Statistics
This disruption started at 7:36 AM on September 16, 2019 and took 2 hours, 8 minutes in total.
For statistics, this disruption is caused due to a signal and level crossing failure.
Operators
This disruption affects trains operated by Arriva.
Got delayed due to this disruption? You may be reimbursed.