Signal and level crossing failure: Groningen-Leeuwarden (17 July 2019)
-
Disruption resolved Last update
Between Groningen and Leeuwarden the train traffic is fully resumed.
- Show complete timeline…
-
Disruption reported
Between Groningen and Leeuwarden there are fewer trains running due to a signal and level crossing failure.
The extra travel time may be up to 30 minutes.
This will take until approximately 7:00 PM hours.
Location of this disruption
This disruption is between Groningen and Leeuwarden.
More about this disruption
Statistics
This disruption started at 4:55 PM on July 17, 2019 and took 1 hour, 46 minutes in total.
For statistics, this disruption is caused due to a signal and level crossing failure.
Operators
This disruption affects trains operated by Arriva.
Got delayed due to this disruption? You may be reimbursed.