Signal and level crossing failure: Eindhoven-Heerlen; Venlo-Roermond (17 December 2017)

  1. Disruption resolved Last update

    Between Swalmen and Roermond the train traffic is fully resumed.
    Between Weert and Sittard the train traffic is fully resumed.

  2. Show complete timeline…
  3. Disruption reported

    Between Weert and Roermond there is a service disruption due to a signal and level crossing failure.
    Updates will follow as more information becomes available.

Location of this disruption

This disruption is between Swalmen and Roermond and between Weert and Sittard.

Map of the location of this disruption

More about this disruption

Statistics

This disruption started at 12:59 PM on December 17, 2017 and took 2 hours, 32 minutes in total.

For statistics, this disruption is caused due to a signal and level crossing failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS and Arriva.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights