Level crossing failure: Eindhoven-Roermond (19 June 2017)
Current status:
This disruption is resolved.
-
Disruption resolved Last update
Between Eindhoven and Roermond the train traffic is fully resumed.
- Show complete timeline…
-
Disruption reported
Between Eindhoven and Roermond there is a service disruption due to a level crossing failure.
Updates will follow as more information becomes available.
Location of this disruption
More about this disruption
Statistics
This disruption started at 7:51 PM on June 19, 2017 and took 55 minutes in total.
For statistics, this disruption is caused due to a level crossing failure.
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.