Disruption cause: level crossing failure

This page shows more information about this disruption cause.

This disruption cause has been categorized under Infrastructure.

Most affected lines

List of the railway lines which are most often affected by this cause.

  1. Eindhoven - Roermond
    12 disruptions • duration: 22 hours
  2. Groningen - Zwolle
    11 disruptions • duration: 21 hours, 28 minutes
  3. Breda - Tilburg
    10 disruptions • duration: 23 hours, 2 minutes
  4. Amersfoort - Apeldoorn
    10 disruptions • duration: 23 hours, 2 minutes
  5. Dordrecht - Geldermalsen
    10 disruptions • duration: 16 hours, 16 minutes

One disruption often impacts multiple railway lines. In those cases, the same disruption is counted for each affected line.

Statistics

Statistics for this cause are calculated over the past 24 months.

Between April 1, 2017 and March 31, 2019, Rijden de Treinen has reported 259 disruptions caused due to a level crossing failure. This is an average of 0 disruptions per day.

The average duration for this cause is 2 hours, 13 minutes.

Number of disruptions and total duration

This graphs shows the number of disruptions which are caused due to a level crossing failure and the total duration of these disruptions (measured in hours).

Disruptions per weekday

This graphs shows the number of disruptions per day of the week.