Disruption cause: unexpected engineering works

This page shows more information about this disruption cause.

This disruption cause has been categorized under Engineering works.

Most affected lines

List of the railway lines which are most often affected by this cause.

  1. Den Haag HS - Rotterdam Centraal
    5 disruptions • duration: 5 hours, 37 minutes
  2. 's-Hertogenbosch - Utrecht Centraal
    4 disruptions • duration: 8 hours, 15 minutes
  3. Leiden Centraal - Schiphol Airport
    3 disruptions • duration: 10 hours, 14 minutes
  4. Arnhem Centraal - Utrecht Centraal
    3 disruptions • duration: 8 hours, 51 minutes
  5. Schiphol Airport - Utrecht Centraal
    3 disruptions • duration: 6 hours, 17 minutes

One disruption often impacts multiple railway lines. In those cases, the same disruption is counted for each affected line.

Statistics

Statistics for this cause are calculated over the past 24 months.

Between February 1, 2017 and January 31, 2019, Rijden de Treinen has reported 43 disruptions caused due to unexpected engineering works. This is an average of 0 disruptions per day.

The average duration for this cause is 1 hour, 48 minutes.

Number of disruptions and total duration

This graphs shows the number of disruptions which are caused due to unexpected engineering works and the total duration of these disruptions (measured in hours).

Disruptions per weekday

This graphs shows the number of disruptions per day of the week.