  1. Breda - Rotterdam Centraal
    40 disruptions • duration: 3 days, 18 hours
  2. Den Haag HS - Rotterdam Centraal
    27 disruptions • duration: 3 days
  3. Den Haag Centraal - Den Haag HS
    22 disruptions • duration: 2 days, 8 hours
  4. Rotterdam Centraal - Utrecht Centraal
    16 disruptions • duration: 2 days, 21 hours
  5. Den Haag Centraal - Utrecht Centraal
    15 disruptions • duration: 4 days, 22 hours

One disruption often impacts multiple railway lines. In those cases, the same disruption is counted for each affected line.

Statistics

Statistics for this cause are calculated over the past 24 months.

Between December 1, 2016 and November 30, 2018, Rijden de Treinen has reported 242 disruptions caused due to damaged overhead wires. This is an average of 0 disruptions per day.

The average duration for this cause is 4 hours, 46 minutes.

Number of disruptions and total duration

This graphs shows the number of disruptions which are caused due to damaged overhead wires and the total duration of these disruptions (measured in hours).

Disruptions per weekday

This graphs shows the number of disruptions per day of the week.