This disruption cause has been categorized under Rolling stock problems.

Most affected lines

List of the railway lines which are most often affected by this cause.

  1. Lelystad Centrum - Schiphol Airport
    224 disruptions • duration: 9 days, 5 hours
  2. Leiden Centraal - Schiphol Airport
    185 disruptions • duration: 6 days, 16 hours
  3. Amersfoort - Schiphol Airport
    177 disruptions • duration: 7 days, 4 hours
  4. Amsterdam Centraal - Schiphol Airport
    177 disruptions • duration: 5 days, 8 hours
  5. Breda - Dordrecht
    138 disruptions • duration: 2 days, 18 hours

One disruption often impacts multiple railway lines. In those cases, the same disruption is counted for each affected line.

Statistics

Statistics for this cause are calculated over the past 24 months.

Between May 1, 2019 and April 30, 2021, Rijden de Treinen has reported 3,568 disruptions caused due to a broken down train. This is an average of 5 disruptions per day.

The average duration for this cause is 40 minutes.

Number of disruptions and total duration

This graphs shows the number of disruptions which are caused due to a broken down train and the total duration of these disruptions (measured in hours).

Disruptions per weekday

This graphs shows the number of disruptions per day of the week.