Signal and level crossing failure: Amersfoort - Deventer (26 August)
-
Disruption resolved Last update
Between Amersfoort Centraal and Deventer the train traffic is fully resumed.
- Show complete timeline…
-
Disruption reported
Between Amersfoort Centraal and Deventer far fewer trains are running due to a signalling and level crossing failure.
This will take until approximately 2:45 PM hours.
Location of this disruption
This disruption is between Amersfoort Centraal and Deventer.
See the disruptions map for a live overview of all disruptions in the Netherlands.
More about this disruption
Statistics
This disruption started at 12:20 PM on August 26, 2025 and took 2 hours, 24 minutes in total.
For statistics, this disruption is caused due to a signal and level crossing failure.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS and NS International.
Got delayed due to this disruption? You may be reimbursed.