Level crossing failure: Venlo - Roermond (18 February)
Current status:
This disruption is resolved.
-
Disruption resolved Last update
Between Swalmen and Roermond the train traffic is fully resumed.
- Show complete timeline…
-
Disruption reported
Between Venlo and Roermond there is a service disruption due to a level crossing failure.
This will take until approximately 10:45 AM hours.
Location of this disruption
More about this disruption
Statistics
This disruption started at 6:35 AM on February 18, 2025 and took 1 hour, 41 minutes in total.
For statistics, this disruption is caused due to a level crossing failure.
Operators
This disruption affects trains operated by Arriva.
Got delayed due to this disruption? You may be reimbursed.