seinstoring

Signal failure: Zwolle - Leeuwarden (5 January)

  1. Disruption resolved Last update

    Between Heerenveen and Akkrum the train traffic is fully resumed.

  2. Show complete timeline…
  3. Disruption reported

    Between Meppel and Leeuwarden there is a service disruption due to a signal failure.
    This will take until approximately 1:45 PM hours.

Location of this disruption

This disruption is between Heerenveen and Akkrum.

Map of the location of this disruption

More about this disruption

Statistics

This disruption started at 11:36 AM on January 5, 2025 and took 2 hours, 44 minutes in total.

For statistics, this disruption is caused due to a signal failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights