Signal and level crossing failure: Roosendaal-Vlissingen (2 January 2024)
-
Disruption resolved Last update
Between Roosendaal and Vlissingen the train traffic is fully resumed.
- Show complete timeline…
-
Disruption reported
Between Roosendaal and Goes there are delays due to a signalling and level crossing failure.
The extra travel time may be up to 30 minutes.
This will take at least until 7:00 PM hours.
Location of this disruption
This disruption is between Roosendaal and Vlissingen.
More about this disruption
Statistics
This disruption started at 6:22 PM on January 2, 2024 and took 3 hours, 21 minutes in total.
For statistics, this disruption is caused due to a signal and level crossing failure.
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.