defecte trein

Broken down train: Den Haag-Rotterdam; Leiden-Rotterdam (28 July 2023)

  1. Disruption resolved Last update

    Between Delft Campus and Schiedam Centrum the train traffic is fully resumed.

  2. Delays decreasing

    Between Delft Campus and Schiedam Centrum the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 10:00 PM hours.

  3. Update

    Between Delft Campus and Schiedam Centrum far fewer trains are running due to a broken down train.
    This will take until approximately 10:00 PM hours.

    Advice

    Use the tram between Den Haag Centraal and Delft.

    Train measures

    • Intercity 2400 Lelystad C./Dordrecht - Dordrecht/Lelystad C. is cancelled between Den Haag HS and Dordrecht
    • Sprinter 5000 Den Haag C./Dordrecht - Dordrecht/Den Haag C. is cancelled between Den Haag Centraal and Schiedam Centrum
    • Sprinter 5100 Den Haag C./Dordrecht - Dordrecht/Den Haag C. is cancelled between Delft Campus and Schiedam Centrum
  4. Update

    Between Delft Campus and Schiedam Centrum far fewer trains are running due to a broken down train.
    This will take until approximately 9:30 PM hours.

    Advice

    Use the tram between Den Haag Centraal and Delft.

    Train measures

    • Intercity 2400 Dordrecht/Lelystad C. - Lelystad C./Dordrecht is cancelled between Den Haag HS and Dordrecht
    • Sprinter 5000 Dordrecht/Den Haag C. - Den Haag C./Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
    • Sprinter 5100 Dordrecht/Den Haag C. - Den Haag C./Dordrecht is cancelled between Delft Campus and Schiedam Centrum
  5. Update

    Between Delft Campus and Schiedam Centrum far fewer trains are running due to a broken down train.
    This will take until approximately 9:00 PM hours.

    Advice

    Use the tram between Den Haag Centraal and Delft.

    Train measures

    • Intercity 2400 Lelystad C./Dordrecht - Dordrecht/Lelystad C. is cancelled between Den Haag HS and Dordrecht
    • Sprinter 5000 Den Haag C./Dordrecht - Dordrecht/Den Haag C. is cancelled between Den Haag Centraal and Schiedam Centrum
    • Sprinter 5100 Den Haag C./Dordrecht - Dordrecht/Den Haag C. is cancelled between Delft Campus and Schiedam Centrum
  6. Update

    Between Delft Campus and Schiedam Centrum far fewer trains are running due to a broken down train.
    This will take until approximately 9:00 PM hours.

    Advice

    Use the tram between Den Haag Centraal and Delft.

    Train measures

    • Sprinter 5000 Dordrecht/Den Haag C. - Den Haag C./Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
    • Sprinter 5100 Dordrecht/Den Haag C. - Den Haag C./Dordrecht is cancelled between Delft Campus and Schiedam Centrum
  7. Update

    Between Delft Campus and Schiedam Centrum far fewer trains are running due to a broken down train.
    This will take until approximately 9:00 PM hours.

    Train measures

    • Sprinter 5000 Dordrecht/Den Haag C. - Den Haag C./Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
    • Sprinter 5100 Dordrecht/Den Haag C. - Den Haag C./Dordrecht is cancelled between Delft Campus and Schiedam Centrum
  8. Update

    Between Delft Campus and Schiedam Centrum far fewer trains are running due to a broken down train.
    This will take until approximately 8:00 PM hours.

    Train measures

    • Sprinter 5000 Dordrecht/Den Haag C. - Den Haag C./Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
    • Sprinter 5100 Dordrecht/Den Haag C. - Den Haag C./Dordrecht is cancelled between Delft Campus and Schiedam Centrum
  9. Update

    Between Delft Campus and Schiedam Centrum far fewer trains are running due to a broken down train.
    This will take until approximately 9:00 PM hours.

  10. Update

    Between Delft Campus and Schiedam Centrum far fewer trains are running due to a broken down train.
    This will take until approximately 8:00 PM hours.

    Train measures

    • Sprinter 5000 Dordrecht/Den Haag C. - Den Haag C./Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
    • Sprinter 5100 Dordrecht/Den Haag C. - Den Haag C./Dordrecht is cancelled between Delft Campus and Schiedam Centrum
  11. Update

    Between Delft Campus and Schiedam Centrum far fewer trains are running due to a broken down train.
    This will take until approximately 7:30 PM hours.

    Train measures

    • Sprinter 5000 Dordrecht/Den Haag C. - Den Haag C./Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
    • Sprinter 5100 Dordrecht/Den Haag C. - Den Haag C./Dordrecht is cancelled between Delft Campus and Schiedam Centrum
  12. Update

    Between Delft Campus and Schiedam Centrum far fewer trains are running due to a broken down train.
    This will take until approximately 7:30 PM hours.

  13. Update

    Between Delft and Rotterdam Centraal there are fewer trains running due to a broken down train.
    This will take until approximately 7:30 PM hours.

  14. Disruption

    Between Delft and Rotterdam Centraal there is a service disruption due to a broken down train.
    This will take until approximately 7:30 PM hours.

More about this disruption

Statistics

This disruption started at 6:30 PM on July 28, 2023 and took 3 hours, 24 minutes in total.

For statistics, this disruption is caused due to a broken down train.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights