Damaged overhead wires: Utrecht-'s-Hertogenbosch (30 January 2021)
-
Disruption resolved Last update
Between Geldermalsen and Culemborg the restrictions are resolved.
- Show complete timeline…
-
Disruption reported
Between Geldermalsen and Culemborg there are fewer trains running due to a broken down train.
This will take until approximately 10:30 PM hours.
Location of this disruption
This disruption is between Geldermalsen and Culemborg.
More about this disruption
Statistics
This disruption started at 10:09 PM on January 30, 2021 and took 1 hour, 40 minutes in total.
For statistics, this disruption is caused due to damaged overhead wires.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.