Signal failure: Groningen-Bad Nieuweschans (12 September 2020)
-
Disruption resolved Last update
Between Zuidbroek and Scheemda the train traffic is fully resumed.
- Show complete timeline…
-
Disruption reported
Between Winschoten and Zuidbroek there are fewer trains running due to a signal failure.
The extra travel time may be up to 60 minutes.
Updates will follow as more information becomes available.
Location of this disruption
This disruption is between Zuidbroek and Scheemda.
See the disruptions map for a live overview of all disruptions in the Netherlands.
More about this disruption
Statistics
This disruption started at 6:12 AM on September 12, 2020 and took 1 hour in total.
For statistics, this disruption is caused due to a signal failure.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by Arriva.
Got delayed due to this disruption? You may be reimbursed.