Broken down train: Utrecht-Den Haag (7 July 2020)
-
Disruption resolved Last update
Between Gouda Goverwelle and Den Haag Centraal the train traffic is fully resumed.
Train measures
- Intercity 1700 Den Haag C. - Amersfoort C. - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
- Intercity 2000 Den Haag C. - Utrecht C. is cancelled between Den Haag Centraal and Utrecht Centraal
- Sprinter 6800 Den Haag C. - Goverwelle is cancelled between Den Haag Centraal and Gouda Goverwelle
- Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
-
Delays decreasing
Between Gouda Goverwelle and Den Haag Centraal the restrictions are resolved.
Delays are decreasing.
Service is normal around 7:00 PM hours.Train measures
- Intercity 1700 Den Haag C. - Amersfoort C. - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
- Intercity 2000 Den Haag C. - Utrecht C. is cancelled between Den Haag Centraal and Utrecht Centraal
- Sprinter 6800 Den Haag C. - Goverwelle is cancelled between Den Haag Centraal and Gouda Goverwelle
- Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
-
Update
Between Gouda Goverwelle and Den Haag Centraal far fewer trains are running due to a broken down train.
This will take until approximately 7:00 PM hours. -
Disruption
Between Den Haag Ypenburg and Zoetermeer there is a service disruption due to a broken down train.
This will take until approximately 7:00 PM hours.
More about this disruption
Statistics
This disruption started at 6:02 PM on July 7, 2020 and took 15 minutes in total.
For statistics, this disruption is caused due to a broken down train.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.