defecte bovenleiding

Damaged overhead wires: Roosendaal-Vlissingen (4 June 2020)

  1. Disruption resolved Last update

    Between Roosendaal and Bergen op Zoom the train traffic is fully resumed.

    Advice

    Local buses are still running between Roosendaal and Bergen op Zoom.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Roosendaal and Bergen op Zoom
  2. Update

    Between Roosendaal and Bergen op Zoom no trains are running due to damaged overhead wires.
    This will take until at least 8:30 AM on Friday, June 5, 2020.

    Advice

    Local buses are running between Roosendaal and Bergen op Zoom.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Roosendaal and Bergen op Zoom
  3. Update

    Between Roosendaal and Bergen op Zoom no trains are running due to damaged overhead wires.
    This will take the rest of the day.

    Advice

    Local buses are running between Roosendaal and Bergen op Zoom.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Roosendaal and Bergen op Zoom
  4. Update

    Between Roosendaal and Bergen op Zoom no trains are running due to a broken down train.
    This will take the rest of the day.

    Advice

    Local buses are running between Roosendaal and Bergen op Zoom.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Roosendaal and Bergen op Zoom
  5. Update

    Between Roosendaal and Bergen op Zoom no trains are running due to a broken down train.
    This will take until at least 10:30 PM hours.

    Advice

    Local buses are running between Roosendaal and Bergen op Zoom.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Roosendaal and Bergen op Zoom
  6. Update

    Between Roosendaal and Bergen op Zoom no trains are running due to a broken down train.
    This will take until at least 10:30 PM hours.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Roosendaal and Bergen op Zoom
  7. Update

    Between Roosendaal and Bergen op Zoom no trains are running due to a broken down train.
    This will take until at least 8:30 PM hours.

    Advice

    Local buses are running between Roosendaal and Bergen op Zoom.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Roosendaal and Bergen op Zoom
  8. Update

    Between Roosendaal and Bergen op Zoom no trains are running due to a broken down train.
    This will take until at least 8:30 PM hours.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Roosendaal and Bergen op Zoom
  9. Update

    Between Roosendaal and Bergen op Zoom no trains are running due to a broken down train.
    This will take until at least 8:30 PM hours.

  10. Update

    Between Roosendaal and Bergen op Zoom no trains are running due to a broken down train.
    It is not known yet how long this will take.

  11. Update

    Between Roosendaal and Bergen op Zoom there are delays and fewer trains are running due to a broken down train.
    It is not known yet how long this will take.

  12. Disruption

    Between Roosendaal and Bergen op Zoom there are delays and fewer trains are running due to a broken down train.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 5:34 PM on June 4, 2020 and took 10 hours, 23 minutes in total.

For statistics, this disruption is caused due to damaged overhead wires.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights