Disruption Sittard-Maastricht; Heerlen-Maastricht Randwyck

Level crossing failure
This disruption is resolved.

Current travel advice

Between Sittard and Maastricht the train traffic is fully resumed.
Between Maastricht and Heerlen the train traffic is fully resumed.

Feb 13, 2020 10:03 PM

Earlier messages

Between Maastricht and Heerlen the restrictions are resolved.
Between Sittard and Maastricht the restrictions are resolved.
Delays are diminishing.
Service is normal around 10:15 PM on Friday, February 14, 2020.

Feb 13, 2020 9:54 PM

Between Sittard and Maastricht there are delays due to a level crossing failure.
Between Maastricht and Heerlen there are delays due to a level crossing failure.
The extra travel time may be up to 15 minutes.
This will take until approximately 10:15 PM on Friday, February 14, 2020.

Feb 13, 2020 9:47 PM

Between Maastricht and Heerlen there are delays due to a level crossing failure.
Between Sittard and Maastricht there are delays due to a level crossing failure.
The extra travel time may be up to 15 minutes.
This will take until approximately 12:15 AM on Friday, February 14, 2020.

Feb 13, 2020 9:47 PM

Between Sittard and Maastricht there are delays due to a level crossing failure.
Between Maastricht and Heerlen there are delays due to a level crossing failure.
The extra travel time may be up to 15 minutes.
This will take until approximately 12:15 AM on Friday, February 14, 2020.

Feb 13, 2020 9:37 PM

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS and Arriva.

Information

This disruption started at 9:37 PM on February 13, 2020 and took 26 minutes in total.

For statistics, this disruption is caused due to a level crossing failure.