Signal and level crossing failure: Alkmaar-Den Helder (22 October 2019)

  1. Disruption resolved Last update

    Between Anna Paulowna and Den Helder the train traffic is fully resumed.

    Train measures

    • Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Anna Paulowna and Den Helder
  2. Show complete timeline…
  3. Disruption reported

    Between Den Helder Zuid and Anna Paulowna there is a service disruption due to a signal and level crossing failure.
    Updates will follow as more information becomes available.

Location of this disruption

This disruption is between Anna Paulowna and Den Helder.

Map of the location of this disruption

More about this disruption

Statistics

This disruption started at 5:33 PM on October 22, 2019 and took 4 hours, 24 minutes in total.

For statistics, this disruption is caused due to a signal and level crossing failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.