  1. Disruption resolved Last update

    Between Amsterdam Centraal and Utrecht Centraal the train traffic is fully resumed.

    Train measures

    • Intercity 2900 Enkhuizen - Utrecht C. - Eindhoven - Maastricht is cancelled between Amsterdam Centraal and Utrecht Centraal
    • Intercity 3100 Schiphol Airport - Utrecht C. - Nijmegen is cancelled between Schiphol Airport and Arnhem Centraal
  2. Delays decreasing

    Between Amsterdam Centraal and Utrecht Centraal the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 11:45 PM hours.

    Train measures

    • Intercity 2900 Enkhuizen - Utrecht C. - Eindhoven - Maastricht is cancelled between Amsterdam Centraal and Utrecht Centraal
    • Intercity 3100 Schiphol Airport - Utrecht C. - Nijmegen is cancelled between Schiphol Airport and Arnhem Centraal
  3. Update

    Between Amsterdam Centraal and Utrecht Centraal fewer intercities are running due to a signal failure.
    This will take until at least 11:30 PM hours.

    Train measures

    • Intercity 2900 Enkhuizen - Utrecht C. - Eindhoven - Maastricht is cancelled between Amsterdam Centraal and Utrecht Centraal
    • Intercity 3100 Schiphol Airport - Utrecht C. - Nijmegen is cancelled between Schiphol Airport and Arnhem Centraal
  4. Update

    Between Amsterdam Centraal and Utrecht Centraal fewer intercities are running due to a signal failure.
    This will take until at least 10:45 PM hours.

    Train measures

    • Intercity 2900 Enkhuizen - Utrecht C. - Eindhoven - Maastricht is cancelled between Amsterdam Centraal and Utrecht Centraal
    • Intercity 3100 Schiphol Airport - Utrecht C. - Nijmegen is cancelled between Schiphol Airport and Arnhem Centraal
  5. Disruption

    Between Amsterdam Centraal and Utrecht Centraal there are delays and fewer trains are running due to a signal failure.
    This will take until at least 10:45 PM hours.

More about this disruption

Statistics

This disruption started at 8:21 PM on July 25, 2019 and took 3 hours, 18 minutes in total.

For statistics, this disruption is caused due to a signal failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS and NS International.

Got delayed due to this disruption? You may be reimbursed.