Signal failure: Den Haag-Rotterdam; Leiden-Rotterdam (2 July 2019)

  1. Disruption resolved Last update

    Between Delft Zuid and Rotterdam Centraal the train traffic is fully resumed.

  2. Delays decreasing

    Between Delft Zuid and Rotterdam Centraal the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 4:30 PM hours.

  3. Update

    Between Delft Zuid and Rotterdam Centraal far fewer trains are running due to a signal failure.
    This will take until at least 4:30 PM hours.

  4. Update

    Between Delft Zuid and Rotterdam Centraal no trains are running due to a signal failure.
    This will take until at least 4:30 PM hours.

  5. Update

    Between Delft Zuid and Schiedam Centrum no trains are running due to a signal failure.
    This will take until at least 4:30 PM hours.

  6. Disruption

    From and to Delft Zuid no trains are running due to a signal failure.
    This will take until at least 4:30 PM hours.

More about this disruption

Statistics

This disruption started at 2:54 PM on July 2, 2019 and took 1 hour, 31 minutes in total.

For statistics, this disruption is caused due to a signal failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.