defecte bovenleiding

Damaged overhead wires: Amsterdam-Schiphol-Rotterdam (HSL) (25 April 2019)

  1. Disruption resolved Last update

    Between Amsterdam Centraal and Rotterdam Centraal the restrictions are resolved.

  2. Update

    Between Amsterdam Centraal and Rotterdam Centraal there is a service disruption due to damaged overhead wires.
    Updates will follow as more information becomes available.

  3. Disruption resolved

    Between Amsterdam Centraal and Rotterdam Centraal the restrictions are resolved.

  4. Delays decreasing

    Between Amsterdam Centraal and Rotterdam Centraal the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 6:45 PM hours.

  5. Update

    Between Amsterdam Centraal and Rotterdam Centraal no Intercity Direct trains are running due to damaged overhead wires.
    This will take until approximately 6:30 PM hours.

  6. Update

    Between Amsterdam Centraal and Rotterdam Centraal no Intercity Direct trains are running due to damaged overhead wires.
    This will take until approximately 6:20 PM hours.

  7. Update

    Between Rotterdam Centraal and Schiphol Airport trains are running via an alternative route due to damaged overhead wires.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 6:20 PM hours.

  8. Update

    Between Rotterdam Centraal and Schiphol Airport trains are running via an alternative route due to damaged overhead wires.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 6:00 PM hours.

  9. Update

    Between Rotterdam Centraal and Schiphol Airport trains are running via an alternative route due to damaged overhead wires.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 5:15 PM hours.

  10. Disruption

    Between Rotterdam Centraal and Schiphol Airport trains are running via an alternative route due to damaged overhead wires.
    The extra travel time may be up to 30 minutes.
    It is not known yet how long this will take.

More about this disruption

Statistics

This disruption started at 3:04 PM on April 25, 2019 and took 6 hours, 49 minutes in total.

For statistics, this disruption is caused due to damaged overhead wires.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS, NS International, Thalys and Eurostar.

Got delayed due to this disruption? You may be reimbursed.