Level crossing failure: Alphen a/d Rijn-Gouda (16 April 2019)

  1. Disruption resolved Last update

    Between Boskoop and Gouda the restrictions are resolved.

    Train measures

    • Sprinter 8600 Gouda - Alphen a/d Rijn is cancelled between Gouda and Boskoop
  2. Delays decreasing

    Between Boskoop and Gouda the restrictions are resolved.
    Delays are diminishing.
    This will take until approximately 11:45 PM hours.

    Advice

    Buses are still running between Boskoop, Boskoop Snijdelwijk, Waddinxveen Noord, Waddinxveen, Waddinxveen Triangel and Gouda.

    Train measures

    • Sprinter 8600 Gouda - Alphen a/d Rijn is cancelled between Gouda and Boskoop
  3. Update

    Between Boskoop and Gouda there are no trains running due to a level crossing failure.
    This will take until approximately 11:45 PM hours.

    Advice

    Local buses are running between Boskoop, Boskoop Snijdelwijk, Waddinxveen Noord, Waddinxveen, Waddinxveen Triangel and Gouda.

    Train measures

    • Sprinter 8600 Gouda - Alphen a/d Rijn is cancelled between Gouda and Boskoop
  4. Update

    Between Boskoop and Gouda there are no trains running due to a level crossing failure.
    This will take until approximately 11:45 PM hours.

    Train measures

    • Sprinter 8600 Gouda - Alphen a/d Rijn is cancelled between Gouda and Boskoop
  5. Update

    Between Boskoop and Gouda there are no trains running due to a level crossing failure.
    This will take until approximately 11:30 PM hours.

    Train measures

    • Sprinter 8600 Gouda - Alphen a/d Rijn is cancelled between Gouda and Boskoop
  6. Update

    Between Boskoop and Gouda there are no trains running due to a level crossing failure.
    This will take the rest of the day.

    Train measures

    • Sprinter 8600 Gouda - Alphen a/d Rijn is cancelled between Gouda and Boskoop
  7. Update

    Between Boskoop and Gouda there are no trains running due to a level crossing failure.
    This will take the rest of the day.

    Train measures

    • Sprinter 8600 Gouda - Alphen a/d Rijn is cancelled between Gouda and Boskoop
    • Sprinter 8700 Gouda - Alphen a/d Rijn is cancelled between Gouda and Boskoop
  8. Update

    Between Boskoop and Gouda there are no trains running due to a level crossing failure.
    This will take until approximately 11:45 PM hours.

    Train measures

    • Sprinter 8600 Gouda - Alphen a/d Rijn is cancelled between Gouda and Boskoop
    • Sprinter 8700 Gouda - Alphen a/d Rijn is cancelled between Gouda and Boskoop
  9. Update

    Between Boskoop and Gouda there are no trains running due to a level crossing failure.
    This will take until approximately 11:45 PM hours.

  10. Update

    Between Boskoop and Gouda there is a service disruption due to a level crossing failure.
    This will take until approximately 11:45 PM hours.

  11. Disruption

    Between Boskoop and Gouda there is a service disruption due to a level crossing failure.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 9:41 PM on April 16, 2019 and took 2 hours, 11 minutes in total.

For statistics, this disruption is caused due to a level crossing failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by R-net.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights