defecte bovenleiding

Damaged overhead wires: Amsterdam-Almere (9 April 2019)

  1. Disruption resolved Last update

    Between Amsterdam Centraal and Almere Centrum the restrictions are resolved.

  2. Delays decreasing

    Between Amsterdam Centraal and Almere Centrum the restrictions are resolved.
    Delays are diminishing.
    Service is normal around 8:45 PM hours.

  3. Delays decreasing

    Between Amsterdam Centraal and Almere Centrum the restrictions are resolved.
    Delays are diminishing.
    Service is normal around 8:30 PM hours.

  4. Delays decreasing

    Between Amsterdam Centraal and Almere Centrum the restrictions are resolved.
    Delays are diminishing.
    This will take until approximately 8:30 PM hours.

  5. Disruption

    Between Amsterdam Centraal and Almere Centrum no intercities are running due to damaged overhead wires.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 8:30 PM hours.

    Train measures

    • Intercity 2600 Amsterdam C. - Almere C. is cancelled between Amsterdam Centraal and Almere Centrum

More about this disruption

Statistics

This disruption started at 5:20 PM on April 9, 2019 and took 3 hours, 18 minutes in total.

For statistics, this disruption is caused due to damaged overhead wires.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights