Signal and level crossing failure: Roermond-Sittard (19 March 2019)
Current status:
This disruption is resolved.
-
Disruption resolved Last update
Between Roermond and Susteren the restrictions are resolved.
Advice
Local buses are running between Echt and Roermond.
Train measures
- Stoptrein 32400 Roermond - Maastricht - Randwyck is cancelled between Roermond and Echt
- Show complete timeline…
-
Disruption reported
Between Roermond and Sittard no trains are running due to a signal and level crossing failure.
It is not known yet how long this will take.
Location of this disruption
More about this disruption
Statistics
This disruption started at 1:51 PM on March 19, 2019 and took 2 hours, 40 minutes in total.
For statistics, this disruption is caused due to a signal and level crossing failure.
Operators
This disruption affects trains operated by NS and Arriva.
Got delayed due to this disruption? You may be reimbursed.