Signal and level crossing failure: Roermond-Sittard (19 March 2019)
Current status:
This disruption is resolved.
-
Disruption resolved Last update
Between Roermond and Sittard the restrictions are resolved.
Train measures
- Intercity 3900 Enkhuizen - Utrecht C. - Eindhoven - Heerlen is cancelled between Roermond and Sittard
- Show complete timeline…
-
Disruption reported
Between Roermond and Sittard there is a service disruption due to a signal failure.
Updates will follow as more information becomes available.
Location of this disruption
More about this disruption
Statistics
This disruption started at 1:39 PM on March 19, 2019 and took 2 hours, 52 minutes in total.
For statistics, this disruption is caused due to a signal and level crossing failure.
Operators
This disruption affects trains operated by NS and Arriva.
Got delayed due to this disruption? You may be reimbursed.