overwegstoring

Level crossing failure: Alkmaar-Den Helder (9 January 2019)

  1. Disruption resolved Last update

    Between Anna Paulowna and Den Helder the restrictions are resolved.

    Advice

    Local buses are running between Anna Paulowna, Den Helder Zuid and Den Helder.

    Train measures

    • Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Anna Paulowna and Den Helder
  2. Update

    Between Anna Paulowna and Den Helder there are no trains running due to a level crossing failure.
    The extra travel time may be up to 30 minutes.
    This will take the rest of the day.

    Advice

    Local buses are running between Anna Paulowna, Den Helder Zuid and Den Helder.

    Train measures

    • Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Anna Paulowna and Den Helder
  3. Update

    Between Anna Paulowna and Den Helder there are no trains running due to a level crossing failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 1:15 AM hours.

    Advice

    Local buses are running between Anna Paulowna, Den Helder Zuid and Den Helder.

    Train measures

    • Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Anna Paulowna and Den Helder
  4. Update

    Between Anna Paulowna and Den Helder there are no trains running due to a level crossing failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 1:00 AM on Thursday, January 10, 2019.

    Advice

    Local buses are running between Anna Paulowna, Den Helder Zuid and Den Helder.

    Train measures

    • Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Anna Paulowna and Den Helder
  5. Update

    Between Anna Paulowna and Den Helder there are no trains running due to a level crossing failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 11:30 PM hours.

    Advice

    Local buses are running between Anna Paulowna, Den Helder Zuid and Den Helder.

    Train measures

    • Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Anna Paulowna and Den Helder
  6. Update

    Between Anna Paulowna and Den Helder there are no trains running due to a level crossing failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 11:30 PM hours.

    Train measures

    • Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Anna Paulowna and Den Helder
  7. Update

    Between Anna Paulowna and Den Helder only shuttle trains are running due to a level crossing failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 11:30 PM hours.

    Train measures

    • Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Anna Paulowna and Den Helder
  8. Update

    Between Anna Paulowna and Den Helder only shuttle trains are running due to a level crossing failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 10:30 PM hours.

    Train measures

    • Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Anna Paulowna and Den Helder
  9. Update

    Between Anna Paulowna and Den Helder only shuttle trains are running due to a level crossing failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 10:00 PM hours.

    Train measures

    • Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Anna Paulowna and Den Helder
  10. Update

    Between Anna Paulowna and Den Helder there are no trains running due to a level crossing failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 10:00 PM hours.

    Train measures

    • Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Anna Paulowna and Den Helder
  11. Update

    Between Anna Paulowna and Den Helder there are no trains running due to a level crossing failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 9:30 PM hours.

    Train measures

    • Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Anna Paulowna and Den Helder
  12. Update

    Between Den Helder Zuid and Alkmaar there are no trains running due to a level crossing failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 9:30 PM hours.

    Train measures

    • Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Anna Paulowna and Den Helder
  13. Update

    Between Den Helder Zuid and Alkmaar there is a service disruption due to a level crossing failure.
    This will take until approximately 9:30 PM hours.

    Train measures

    • Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Anna Paulowna and Den Helder
  14. Update

    Between Den Helder Zuid and Alkmaar there is a service disruption due to a level crossing failure.
    Updates will follow as more information becomes available.

  15. Disruption

    Between Den Helder and Den Helder Zuid there are no trains running due to a level crossing failure.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 7:39 PM on January 9, 2019 and took 5 hours, 39 minutes in total.

For statistics, this disruption is caused due to a level crossing failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights