seinstoring

Signal failure: Utrecht-Amersfoort (25 July 2018)

  1. Disruption resolved Last update

    Between Utrecht Centraal and Amersfoort the train traffic is fully resumed.

  2. Show complete timeline…
  3. Disruption reported

    Between Amersfoort and Den Dolder no intercities are running due to a signal failure.
    This will take until approximately 7:30 AM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Utrecht Centraal and Amersfoort
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Utrecht Centraal and Amersfoort
    • Intercity 1700 Den Haag C. - Amersfoort - Hengelo - Enschede is cancelled between Utrecht Centraal and Amersfoort
    • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Utrecht Centraal and Amersfoort Schothorst
  4. Update

    Between Amersfoort and Den Dolder there is a service disruption due to a signal failure.
    Updates will follow as more information becomes available.

Location of this disruption

This disruption is between Utrecht Centraal and Amersfoort.

Map of the location of this disruption

More about this disruption

Statistics

This disruption started at 5:55 AM on July 25, 2018 and took 6 hours, 25 minutes in total.

For statistics, this disruption is caused due to a signal failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights