defecte bovenleiding

Damaged overhead wires: Lelystad-Zwolle (23 July 2018)

  1. Disruption resolved Last update

    Between Lelystad Centrum and Zwolle the train traffic is fully resumed.

  2. Delays decreasing

    Between Lelystad Centrum and Zwolle the restrictions are resolved.
    Delays are diminishing.
    Service is normal around 8:00 PM hours.

  3. Update

    Between Lelystad Centrum and Zwolle no intercities are running due to damaged overhead wires.
    This will take until approximately 8:30 PM hours.

    Advice

    Passengers between Schiphol Airport and Zwolle may also travel via Utrecht Centraal. The extra travel time is up to 15 minutes.

    Train measures

    • Intercity 700 Den Haag C. - Schiphol Airport - Lelystad C. - Groningen is cancelled between Lelystad Centrum and Zwolle
    • Intercity 1800 Den Haag C. - Schiphol Airport - Lelystad C. - Leeuwarden is cancelled between Lelystad Centrum and Zwolle
  4. Update

    Between Lelystad Centrum and Zwolle no intercities are running due to damaged overhead wires.
    This will take until approximately 4:30 PM hours.

    Advice

    Passengers between Schiphol Airport and Zwolle may also travel via Utrecht Centraal. The extra travel time is up to 15 minutes.

    Train measures

    • Intercity 700 Den Haag C. - Schiphol Airport - Lelystad C. - Groningen is cancelled between Lelystad Centrum and Zwolle
    • Intercity 1800 Den Haag C. - Schiphol Airport - Lelystad C. - Leeuwarden is cancelled between Lelystad Centrum and Zwolle
  5. Update

    Between Lelystad Centrum and Zwolle no intercities are running due to damaged overhead wires.
    This will take until approximately 3:30 PM hours.

    Advice

    Passengers between Schiphol Airport and Zwolle may also travel via Utrecht Centraal. The extra travel time is up to 15 minutes.

    Train measures

    • Intercity 700 Den Haag C. - Schiphol Airport - Lelystad C. - Groningen is cancelled between Lelystad Centrum and Zwolle
    • Intercity 1800 Den Haag C. - Schiphol Airport - Lelystad C. - Leeuwarden is cancelled between Lelystad Centrum and Zwolle
  6. Update

    Between Lelystad Centrum and Zwolle no intercities are running due to damaged overhead wires.
    This will take until approximately 11:45 AM hours.

    Advice

    Passengers between Schiphol Airport and Zwolle may also travel via Utrecht Centraal. The extra travel time is up to 15 minutes.

    Train measures

    • Intercity 700 Den Haag C. - Schiphol Airport - Lelystad C. - Groningen is cancelled between Lelystad Centrum and Zwolle
    • Intercity 1800 Den Haag C. - Schiphol Airport - Lelystad C. - Leeuwarden is cancelled between Lelystad Centrum and Zwolle
  7. Update

    Between Lelystad Centrum and Zwolle no intercities are running due to damaged overhead wires.
    This will take until approximately 11:45 AM hours.

    Train measures

    • Intercity 700 Den Haag C. - Schiphol Airport - Lelystad C. - Groningen is cancelled between Lelystad Centrum and Zwolle
    • Intercity 1800 Den Haag C. - Schiphol Airport - Lelystad C. - Leeuwarden is cancelled between Lelystad Centrum and Zwolle
  8. Update

    Between Lelystad Centrum and Zwolle no intercities are running due to damaged overhead wires.
    It is not known yet how long this will take.

    Train measures

    • Intercity 700 Den Haag C. - Schiphol Airport - Lelystad C. - Groningen is cancelled between Lelystad Centrum and Zwolle
    • Intercity 1800 Den Haag C. - Schiphol Airport - Lelystad C. - Leeuwarden is cancelled between Lelystad Centrum and Zwolle
  9. Update

    Between Lelystad Centrum and Zwolle no intercities are running due to damaged overhead wires.
    It is not known yet how long this will take.

  10. Update

    Between Lelystad Centrum and Kampen Zuid no intercities are running due to damaged overhead wires.
    It is not known yet how long this will take.

  11. Disruption

    Between Lelystad Centrum and Kampen Zuid there is a service disruption due to damaged overhead wires.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 6:30 AM on July 23, 2018 and took 13 hours, 25 minutes in total.

For statistics, this disruption is caused due to damaged overhead wires.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights