overwegstoring

Level crossing failure: Utrecht-Alphen a/d Rijn (10 July 2018)

  1. Disruption resolved Last update

    Between Bodegraven and Alphen a/d Rijn the train traffic is fully resumed.

  2. Show complete timeline…
  3. Disruption reported

    Between Bodegraven and Alphen a/d Rijn no trains are running due to a level crossing failure.
    This will take until approximately 10:45 AM hours.

  4. Update

    Between Utrecht Centraal and Alphen a/d Rijn there are delays and fewer trains are running due to a level crossing failure.
    It is not known yet how long this will take.

Location of this disruption

This disruption is between Bodegraven and Alphen a/d Rijn.

Map of the location of this disruption

More about this disruption

Statistics

This disruption started at 9:01 AM on July 10, 2018 and took 1 hour, 41 minutes in total.

For statistics, this disruption is caused due to a level crossing failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights