Level crossing failure: Nijmegen-Venlo (14 June 2018)
Current status:
This disruption is resolved.
-
Disruption resolved Last update
Between Boxmeer and Venray the train traffic is fully resumed.
- Show complete timeline…
-
Disruption reported
Between Boxmeer and Venray there is a service disruption due to a level crossing failure.
Updates will follow as more information becomes available.
Location of this disruption
More about this disruption
Statistics
This disruption started at 2:47 PM on June 14, 2018 and took 3 hours, 2 minutes in total.
For statistics, this disruption is caused due to a level crossing failure.
Operators
This disruption affects trains operated by Arriva.
Got delayed due to this disruption? You may be reimbursed.