overwegstoring

Level crossing failure: Venlo-Roermond; Nijmegen-Venray (19 January 2018)

  1. Disruption resolved Last update

    Between Nijmegen and Cuijk the train traffic is fully resumed.
    Between Venlo and Roermond the train traffic is fully resumed.

  2. Delays decreasing

    Between Venlo and Roermond the restrictions are resolved.
    Between Nijmegen and Cuijk the restrictions are resolved.
    Delays are diminishing.
    Service is normal around 10:30 AM hours.

  3. Update

    Between Nijmegen and Cuijk there are fewer trains running due to a level crossing failure.
    Between Venlo and Roermond there are delays due to a level crossing failure.
    This will take until approximately 10:30 AM hours.

  4. Update

    Between Nijmegen and Mook Molenhoek there are fewer trains running due to a level crossing failure.
    This will take until approximately 10:30 AM hours.

  5. Update

    Between Nijmegen and Mook Molenhoek there are fewer trains running due to a level crossing failure.
    This will take until approximately 10:00 AM hours.

  6. Update

    Between Nijmegen and Mook Molenhoek there are no trains running due to a level crossing failure.
    This will take until approximately 10:00 AM hours.

  7. Disruption

    Between Nijmegen and Mook Molenhoek there are no trains running due to a level crossing failure.
    It is not known yet how long this will take.

More about this disruption

Statistics

This disruption started at 7:00 AM on January 19, 2018 and took 3 hours, 33 minutes in total.

For statistics, this disruption is caused due to a level crossing failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by Arriva.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights