Disruption Utrecht-Amersfoort; Utrecht-Baarn

Signal failure
This disruption is resolved.

Current travel advice

Between Utrecht Overvecht and Den Dolder the train traffic is fully resumed.

Oct 30, 2017 7:53 AM

Earlier messages

Between Utrecht Overvecht and Den Dolder the restrictions are resolved.
Delays are diminishing.
Service is normal around 7:45 AM hours.

Oct 30, 2017 7:28 AM

Between Utrecht Overvecht and Den Dolder there are no trains running due to a signal failure.
It is not known yet how long this will take.

Oct 30, 2017 6:24 AM

Between Utrecht Overvecht and Bilthoven there is a service disruption due to a signal failure.
Updates will follow as more information becomes available.

Oct 30, 2017 6:16 AM

Between Bilthoven and Den Dolder there is a service disruption due to a signal failure.
Updates will follow as more information becomes available.

Oct 30, 2017 6:07 AM

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Information

This disruption started at 6:07 AM on October 30, 2017 and took 1 hour, 47 minutes in total.

For statistics, this disruption is caused due to a signal failure.