Signal failure: Eindhoven-Venlo (14 October 2017)

  1. Disruption resolved Last update

    Between Blerick and Venlo the train traffic is fully resumed.

  2. Delays decreasing

    Between Blerick and Venlo the restrictions are resolved.
    Delays are diminishing.
    Service is normal around 9:45 PM hours.

    Train measures

    • Intercity 13500 Eindhoven - Venlo is cancelled between Blerick and Venlo
  3. Update

    Between Blerick and Venlo no intercities are running due to a signal failure.
    It is not known yet how long this will take.

    Train measures

    • Intercity 13500 Eindhoven - Venlo is cancelled between Blerick and Venlo
  4. Update

    Between Blerick and Venlo no intercities are running due to a signal failure.
    Service is normal around 10:00 PM hours.

    Train measures

    • Intercity 13500 Eindhoven - Venlo is cancelled between Blerick and Venlo
  5. Update

    Between Blerick and Venlo no intercities are running due to a signal failure.
    Service is normal around 9:30 PM hours.

    Train measures

    • Intercity 13500 Eindhoven - Venlo is cancelled between Blerick and Venlo
  6. Update

    Between Blerick and Venlo no intercities are running due to a signal failure.
    Service is normal around 9:30 PM hours.

  7. Disruption resolved

    Between Blerick and Venlo the train traffic is fully resumed.

  8. Delays decreasing

    Between Blerick and Venlo the restrictions are resolved.
    Delays are diminishing.
    Service is normal around 8:00 PM hours.

  9. Update

    Between Blerick and Venlo no intercities are running due to a signal failure.
    This will take until approximately 8:30 PM hours.

    Train measures

    • Intercity 13500 Eindhoven - Venlo is cancelled between Blerick and Venlo
  10. Disruption

    Between Blerick and Venlo no intercities are running due to a signal failure.
    This will take until approximately 7:30 PM hours.

    Train measures

    • Intercity 13500 Eindhoven - Venlo is cancelled between Blerick and Venlo

More about this disruption

Statistics

This disruption started at 4:31 PM on October 14, 2017 and took 5 hours, 13 minutes in total.

For statistics, this disruption is caused due to a signal failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS and Arriva.

Got delayed due to this disruption? You may be reimbursed.