sein- en overwegstoring

Signal and level crossing failure: Sittard-Heerlen (14 July 2017)

  1. Disruption resolved Last update

    Between Sittard and Heerlen the train traffic is fully resumed.

  2. Show complete timeline…
  3. Disruption reported

    Between Sittard and Heerlen far fewer trains are running due to a signal and level crossing failure.
    It is not known yet how long this will take.

    Train measures

    • Intercity 3500 Schiphol Airport - Utrecht C. - Eindhoven - Heerlen is cancelled between Sittard and Heerlen
    • Stoptrein 32500 Sittard - Heerlen - Kerkrade C. runs only once per hour between Sittard and Heerlen
  4. Update

    Between Sittard and Heerlen there are delays and fewer trains are running due to a signal and level crossing failure.
    It is not known yet how long this will take.

Location of this disruption

This disruption is between Sittard and Heerlen.

Map of the location of this disruption

See the disruptions map for a live overview of all disruptions in the Netherlands.

More about this disruption

Statistics

This disruption started at 4:03 PM on July 14, 2017 and took 6 hours, 5 minutes in total.

For statistics, this disruption is caused due to a signal and level crossing failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS and Arriva.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights