Damaged overhead wires: Utrecht-Rhenen (5 July 2017)

  1. Disruption resolved Last update

    Between Utrecht Centraal and Veenendaal Centrum the train traffic is fully resumed.

    Advice

    Local buses are still running between Driebergen-Zeist, Veenendaal West and Veenendaal Centrum.
    Local buses are still running between Bunnik, Driebergen-Zeist and Maarn.

  2. Show complete timeline…
  3. Disruption reported

    Between Utrecht Centraal and Driebergen-Zeist there is a service disruption due to a stranded train.
    Between Utrecht Centraal and Rhenen there is a service disruption due to a stranded train.
    Updates will follow as more information becomes available.

Location of this disruption

This disruption is between Utrecht Centraal and Veenendaal Centrum.

Map of the location of this disruption

More about this disruption

Statistics

This disruption started at 3:55 PM on July 5, 2017 and took 6 hours, 5 minutes in total.

For statistics, this disruption is caused due to damaged overhead wires.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights