Damaged overhead wires: Eindhoven-Venlo (2 June 2017)

  1. Disruption resolved Last update

    Between Eindhoven and Venlo the train traffic is fully resumed.

  2. Delays decreasing

    Between Eindhoven and Venlo the restrictions are resolved.
    Delays are diminishing.
    Service is normal around 6:30 AM hours.

  3. Update

    Between Eindhoven and Venlo there are delays and fewer trains are running due to damaged overhead wires.
    The extra travel time may be up to 45 minutes.
    Service is normal around 6:30 AM hours.

  4. Update

    Between Eindhoven and Venlo there are delays and fewer trains are running due to damaged overhead wires.
    The extra travel time may be up to 45 minutes.
    It is not known yet how long this will take.

  5. Disruption

    Between Eindhoven and Venlo there is a service disruption due to damaged overhead wires.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 5:23 AM on June 2, 2017 and took 1 hour, 8 minutes in total.

For statistics, this disruption is caused due to damaged overhead wires.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.