Disruption Eindhoven-Venlo

Damaged overhead wires
This disruption is resolved.

Current travel advice

Between Eindhoven and Venlo the train traffic is fully resumed.

Apr 26, 2017 9:58 PM

Earlier messages

Between Eindhoven and Venlo the restrictions are resolved.
Delays are diminishing.
Service is normal around 10:00 PM hours.

Apr 26, 2017 9:44 PM

Between Eindhoven and Venlo there are delays due to damaged overhead wires.
The extra travel time may be up to 30 minutes.
This will take until approximately 10:15 PM hours.

Apr 26, 2017 9:21 PM

Between Eindhoven and Venlo there are delays due to damaged overhead wires.
The extra travel time may be up to 30 minutes.
This will take until approximately 10:00 PM hours.

Apr 26, 2017 9:19 PM

Between Eindhoven and Venlo there are delays due to damaged overhead wires.
The extra travel time may be up to 30 minutes.
This will take until approximately 12:15 AM on Thursday, April 27, 2017.

Apr 26, 2017 8:41 PM

Between Eindhoven and Venlo there are delays due to damaged overhead wires.
The extra travel time may be up to 30 minutes.
It is not known yet how long this will take.

Apr 26, 2017 7:56 PM

Between Deurne and Horst-Sevenum there is a service disruption due to damaged overhead wires.
Updates will follow as more information becomes available.

Apr 26, 2017 7:33 PM

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Information

This disruption started at 7:33 PM on April 26, 2017 and took 2 hours, 25 minutes in total.

For statistics, this disruption is caused due to damaged overhead wires.