Disruption Eindhoven-Venlo

Level crossing failure
This disruption is resolved.

Current travel advice

Between Eindhoven and Helmond the train traffic is fully resumed.

Mar 30, 2017 6:45 PM

Earlier messages

Between Eindhoven and Helmond the restrictions are resolved.
Delays are diminishing.
Service is normal around 6:45 PM hours.

Mar 30, 2017 6:25 PM

Between Eindhoven and Helmond there are no trains running due to a level crossing failure.
The extra travel time is more than 60 minutes.
It is not known yet how long this will take.

Mar 30, 2017 6:04 PM

Between Eindhoven and Deurne there is a service disruption due to a broken down train.
Updates will follow as more information becomes available.

Mar 30, 2017 5:56 PM

Between Eindhoven and Deurne there is a service disruption due to a broken down train.
The extra travel time may be up to 15 minutes.
Updates will follow as more information becomes available.

Mar 30, 2017 5:55 PM

Between Eindhoven and Deurne the restrictions are resolved.
Delays are diminishing.
Service is normal around 6:00 PM hours.

Mar 30, 2017 5:48 PM

Between Eindhoven and Deurne there are delays due to a broken down train.
The extra travel time may be up to 15 minutes.
It is not known yet how long this will take.

Mar 30, 2017 5:21 PM

Between Eindhoven and Deurne there is a service disruption due to a broken down train.
Updates will follow as more information becomes available.

Mar 30, 2017 4:58 PM

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Information

This disruption started at 4:58 PM on March 30, 2017 and took 1 hour, 47 minutes in total.

For statistics, this disruption is caused due to a level crossing failure.