Disruption Haarlem-Hoorn

Signal and level crossing failure
This disruption is resolved.

Current travel advice

Between Heerhugowaard and Hoorn the train traffic is fully resumed.

Mar 17, 2017 5:29 PM

Earlier messages

Between Heerhugowaard and Hoorn the restrictions are resolved.
Delays are diminishing.
Service is normal around 5:30 PM hours.

Mar 17, 2017 4:57 PM

Between Heerhugowaard and Hoorn there are no trains running due to a signal and level crossing failure.
The extra travel time may be up to 30 minutes.
This will take until at least 5:15 PM hours.

Advice

Local buses are running between Heerhugowaard, Obdam and Hoorn.

Train measures

  • Intercity 4500 Enkhuizen - Zaandam - Amsterdam CS will make an extra stop at Zaandam
  • Sprinter 4800 Amsterdam CS - Haarlem - Hoorn is cancelled between Heerhugowaard and Hoorn
  • Intercity 14500 Amsterdam CS - Enkhuizen will make an extra stop at Zaandam
Mar 17, 2017 3:59 PM

Between Heerhugowaard and Hoorn there are no trains running due to a signal and level crossing failure.
The extra travel time may be up to 30 minutes.
This will take until at least 4:45 PM hours.

Advice

Local buses are running between Heerhugowaard, Obdam and Hoorn.

Train measures

  • Intercity 4500 Enkhuizen - Zaandam - Amsterdam CS will make an extra stop at Zaandam
  • Sprinter 4800 Amsterdam CS - Haarlem - Hoorn is cancelled between Heerhugowaard and Hoorn
  • Intercity 14500 Amsterdam CS - Enkhuizen will make an extra stop at Zaandam
Mar 17, 2017 3:57 PM

Between Heerhugowaard and Hoorn there are no trains running due to a signal and level crossing failure.
This will take until at least 4:45 PM hours.

Train measures

  • Intercity 4500 Enkhuizen - Zaandam - Amsterdam CS will make an extra stop at Zaandam
  • Sprinter 4800 Amsterdam CS - Haarlem - Hoorn is cancelled between Heerhugowaard and Hoorn
  • Intercity 14500 Amsterdam CS - Enkhuizen will make an extra stop at Zaandam
Mar 17, 2017 3:30 PM

Between Heerhugowaard and Hoorn there are no trains running due to a signal and level crossing failure.
This will take until at least 3:45 PM hours.

Train measures

  • Intercity 4500 Enkhuizen - Zaandam - Amsterdam CS will make an extra stop at Zaandam
  • Sprinter 4800 Amsterdam CS - Haarlem - Hoorn is cancelled between Heerhugowaard and Hoorn
  • Intercity 14500 Amsterdam CS - Enkhuizen will make an extra stop at Zaandam
Mar 17, 2017 2:39 PM

Between Heerhugowaard and Hoorn there are no trains running due to a points failure.
This will take until at least 3:45 PM hours.

Train measures

  • Intercity 4500 Enkhuizen - Zaandam - Amsterdam CS will make an extra stop at Zaandam
  • Sprinter 4800 Amsterdam CS - Haarlem - Hoorn is cancelled between Heerhugowaard and Hoorn
  • Intercity 14500 Amsterdam CS - Enkhuizen will make an extra stop at Zaandam
Mar 17, 2017 2:35 PM

Between Heerhugowaard and Hoorn there are no trains running due to a points failure.
This will take until approximately 3:45 PM hours.

Train measures

  • Intercity 4500 Enkhuizen - Zaandam - Amsterdam CS will make an extra stop at Zaandam
  • Sprinter 4800 Amsterdam CS - Haarlem - Hoorn is cancelled between Heerhugowaard and Hoorn
  • Intercity 14500 Amsterdam CS - Enkhuizen will make an extra stop at Zaandam
Mar 17, 2017 2:34 PM

Between Heerhugowaard and Hoorn there are no trains running due to a points failure.
It is not known yet how long this will take.

Train measures

  • Intercity 4500 Enkhuizen - Zaandam - Amsterdam CS will make an extra stop at Zaandam
  • Sprinter 4800 Amsterdam CS - Haarlem - Hoorn is cancelled between Heerhugowaard and Hoorn
  • Intercity 14500 Amsterdam CS - Enkhuizen will make an extra stop at Zaandam
Mar 17, 2017 2:20 PM

Between Heerhugowaard and Hoorn there are no trains running due to a points failure.
It is not known yet how long this will take.

Mar 17, 2017 2:16 PM

Between Heerhugowaard and Hoorn there is a service disruption due to a points failure.
Updates will follow as more information becomes available.

Mar 17, 2017 2:05 PM

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Information

This disruption started at 2:05 PM on March 17, 2017 and took 3 hours, 23 minutes in total.

For statistics, this disruption is caused due to a signal and level crossing failure.