sein- en wisselstoring

Signalling and points failure: Eindhoven-Heerlen (26 February 2017)

  1. Disruption resolved Last update

    Between Eindhoven and Sittard the train traffic is fully resumed.

  2. Delays decreasing

    Between Eindhoven and Sittard the restrictions are resolved.
    Delays are diminishing.
    Service is normal around 9:00 PM hours.

  3. Update

    Between Eindhoven and Sittard fewer intercities are running due to a signalling and points failure.
    This will take until at least 9:00 PM hours.

    Train measures

    • Intercity 800 Alkmaar - Utrecht C. - Eindhoven - Maastricht with an extra change at Eindhoven between 's-Hertogenbosch and Roermond
    • Intercity 3500 Schiphol Airport - Utrecht C. - Eindhoven - Heerlen is cancelled between Eindhoven and Sittard
  4. Update

    Between Eindhoven and Sittard fewer intercities are running due to a signalling and points failure.
    This will take until at least 8:30 PM hours.

    Train measures

    • Intercity 800 Alkmaar - Utrecht C. - Eindhoven - Maastricht with an extra change at Eindhoven between 's-Hertogenbosch and Roermond
    • Intercity 3500 Schiphol Airport - Utrecht C. - Eindhoven - Heerlen is cancelled between Eindhoven and Sittard
  5. Update

    Between Eindhoven and Sittard fewer intercities are running due to a signalling and points failure.
    This will take until at least 8:00 PM hours.

    Train measures

    • Intercity 800 Alkmaar - Utrecht C. - Eindhoven - Maastricht with an extra change at Eindhoven between 's-Hertogenbosch and Roermond
    • Intercity 3500 Schiphol Airport - Utrecht C. - Eindhoven - Heerlen is cancelled between Eindhoven and Sittard
  6. Update

    Between Eindhoven and Sittard fewer intercities are running due to a signalling and points failure.
    This will take until at least 7:30 PM hours.

    Train measures

    • Intercity 800 Alkmaar - Utrecht C. - Eindhoven - Maastricht with an extra change at Eindhoven between 's-Hertogenbosch and Roermond
    • Intercity 3500 Schiphol Airport - Utrecht C. - Eindhoven - Heerlen is cancelled between Eindhoven and Sittard
  7. Update

    Between Eindhoven and Sittard fewer intercities are running due to a signalling and points failure.
    This will take until at least 6:30 PM hours.

    Train measures

    • Intercity 800 Alkmaar - Utrecht C. - Eindhoven - Maastricht with an extra change at Eindhoven between 's-Hertogenbosch and Roermond
    • Intercity 3500 Schiphol Airport - Utrecht C. - Eindhoven - Heerlen is cancelled between Eindhoven and Sittard
  8. Update

    Between Eindhoven and Sittard fewer intercities are running due to a signalling and points failure.
    Between Sittard and Heerlen no intercities are running due to a signalling and points failure.
    It is not known yet how long this will take.

    Advice

    Express buses are running between Sittard and Roermond.

    Train measures

    • Intercity 800 Alkmaar - Utrecht C. - Eindhoven - Maastricht with an extra change at Eindhoven between 's-Hertogenbosch and Roermond
    • Intercity 3500 Schiphol Airport - Utrecht C. - Eindhoven - Heerlen is cancelled between Eindhoven and Heerlen
  9. Update

    Between Eindhoven and Sittard fewer intercities are running due to a signalling and points failure.
    Between Sittard and Heerlen no intercities are running due to a signalling and points failure.
    This will take until at least 4:00 PM hours.

    Advice

    Express buses are running between Sittard and Roermond.

    Train measures

    • Intercity 800 Alkmaar - Utrecht C. - Eindhoven - Maastricht with an extra change at Eindhoven between 's-Hertogenbosch and Roermond
    • Intercity 3500 Schiphol Airport - Utrecht C. - Eindhoven - Heerlen is cancelled between Eindhoven and Heerlen
  10. Update

    Between Eindhoven and Sittard fewer intercities are running due to a signalling and points failure.
    Between Sittard and Heerlen no intercities are running due to a signalling and points failure.
    This will take until at least 3:00 PM hours.

    Advice

    Express buses are running between Sittard and Roermond.

    Train measures

    • Intercity 800 Alkmaar - Utrecht C. - Eindhoven - Maastricht with an extra change at Eindhoven between 's-Hertogenbosch and Roermond
    • Intercity 3500 Schiphol Airport - Utrecht C. - Eindhoven - Heerlen is cancelled between Eindhoven and Heerlen
  11. Update

    Between Eindhoven and Sittard fewer intercities are running due to a signalling and points failure.
    Between Sittard and Heerlen no intercities are running due to a signalling and points failure.
    This will take until at least 3:00 PM hours.

    Train measures

    • Intercity 800 Alkmaar - Utrecht C. - Eindhoven - Maastricht with an extra change at Eindhoven between 's-Hertogenbosch and Roermond
    • Intercity 3500 Schiphol Airport - Utrecht C. - Eindhoven - Heerlen is cancelled between Eindhoven and Heerlen
  12. Update

    Between Eindhoven and Sittard there are delays and fewer trains are running due to a signalling and points failure.
    It is not known yet how long this will take.

  13. Update

    Between Eindhoven and Sittard there are delays and fewer trains are running due to a defective point.
    It is not known yet how long this will take.

  14. Delays decreasing

    Between Eindhoven and Weert the restrictions are resolved.
    Delays are diminishing.
    Service is normal around 12:45 PM hours.

  15. Disruption

    Between Eindhoven and Weert there are delays due to a defective point.
    The extra travel time may be up to 15 minutes.
    It is not known yet how long this will take.

More about this disruption

Statistics

This disruption started at 12:07 PM on February 26, 2017 and took 8 hours, 53 minutes in total.

For statistics, this disruption is caused due to a signalling and points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS and Arriva.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights