Level crossing failure: Eindhoven-Venlo (3 February 2017)
Current status:
This disruption is resolved.
-
Disruption resolved Last update
Between Eindhoven and Deurne the train traffic is fully resumed.
Train measures
- Sprinter 9600 Deurne - Eindhoven - 's-Hertogenbosch is cancelled between Eindhoven and Deurne
- Extra trein 29750-29799 Eindhoven - Amsterdam CS calls at all intermediate stations between Eindhoven and Venlo
- Show complete timeline…
-
Disruption reported
Between Eindhoven and Deurne there is a service disruption due to a level crossing failure.
Updates will follow as more information becomes available.
Location of this disruption
More about this disruption
Statistics
This disruption started at 5:27 PM on February 3, 2017 and took 6 hours, 47 minutes in total.
For statistics, this disruption is caused due to a level crossing failure.
Operators
This disruption affects trains operated by NS.