Engineering works: Utrecht Centraal
Situation
From and to Utrecht Centraal the timetable has been changed due to engineering works.
The extra travel time may be up to 30 minutes.
Period
On Saturday, December 19, 2020 between 2:00 AM and 7:20 AM hours.
Modified timetable
During these engineering works, the timetable has been modified. The following changes have been made to the train schedule:
- Intercity 1400 Rotterdam C. - Leiden C. - Amsterdam C. - Utrecht C. is cancelled between Amsterdam Centraal and Utrecht Centraal
- Sprinter 5700 Utrecht C. - Hilversum - Hoofddorp is cancelled between Utrecht Centraal and Weesp (only in direction of Weesp)
- Sprinter 7300 Veenendaal C. - Utrecht C. - Breukelen is cancelled between Rhenen and Utrecht Centraal (only in direction of Utrecht Centraal)
- Sprinter 7400 Uitgeest - Amsterdam C. - Utrecht C. - Rhenen is cancelled between Utrecht Centraal and Amsterdam Centraal (only in direction of Amsterdam Centraal)
- Sprinter 14000 Utrecht C. - Rotterdam C. is cancelled between Utrecht Centraal and Rotterdam Centraal (only in direction of Rotterdam Centraal)
- Niet instappen 21500 to 21506 Amsterdam C. - Utrecht C. is cancelled between Amsterdam Centraal and Utrecht Centraal
- Buses are running between Amsterdam Centraal and Utrecht Centraal.
- Buses are running between Utrecht Centraal, Utrecht Zuilen, Maarssen, Breukelen, Abcoude, Amsterdam Holendrecht, Amsterdam Bijlmer ArenA, Duivendrecht, Amsterdam Amstel, Amsterdam Muiderpoort and Amsterdam Centraal.
- Buses are running between Utrecht Centraal, Utrecht Zuilen, Maarssen, Breukelen and Abcoude.
More about these engineering works
Plan your trip
Plan your trip in advance and use the journey planner.
During your trip, you can stay up-to-date by checking live departures or by using the Rijden de Treinen mobile app for iOS and Android.
Affected lines
The following lines are affected by these engineering works:
- Hilversum - Utrecht Centraal
- Baarn - Utrecht Centraal
- Utrecht Centraal - Utrecht Maliebaan
- Arnhem Centraal - Utrecht Centraal
- Amersfoort - Utrecht Centraal
- Amsterdam Centraal - Utrecht Centraal
- Schiphol Airport - Utrecht Centraal
- Rotterdam Centraal - Utrecht Centraal
- Den Haag Centraal - Utrecht Centraal
- Leiden Centraal - Utrecht Centraal
- Almere Oostvaarders - Utrecht Centraal
- Tiel - Utrecht Centraal
- 's-Hertogenbosch - Utrecht Centraal
- Rhenen - Utrecht Centraal
Time periods
These engineering works are in effect between Saturday, December 19, 2020 2:00 AM and Saturday, December 19, 2020 7:20 AM.