Points failure: Leiden - Rotterdam (10 March)

  1. Disruption resolved Last update

    Between Leiden Centraal and Rotterdam Centraal the train traffic is fully resumed.

  2. Show complete timeline…
  3. Disruption reported

    Between Leiden Centraal and Rotterdam Centraal fewer intercities are running due to a points failure.
    The extra travel time may be up to 15 minutes.
    This will take until approximately 8:45 AM hours.

Location of this disruption

This disruption is between Leiden Centraal and Rotterdam Centraal.

Map of the location of this disruption

More about this disruption

Statistics

This disruption started at 6:18 AM on March 10, 2025 and took 1 hour, 42 minutes in total.

For statistics, this disruption is caused due to a points failure.

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.