Damaged level crossing: Schiphol - Utrecht (4 September 2024)
-
Disruption resolved Last update
Between Utrecht Centraal and Schiphol Airport the train traffic is fully resumed.
- Show complete timeline…
-
Disruption reported
Between Schiphol Airport and Utrecht Centraal fewer intercities are running due to a damaged level crossing.
The extra travel time may be up to 15 minutes.
This will take until approximately 10:15 AM hours.
Location of this disruption
This disruption is between Utrecht Centraal and Schiphol Airport.
More about this disruption
Statistics
This disruption started at 7:56 AM on September 4, 2024 and took 5 hours, 4 minutes in total.
For statistics, this disruption is caused due to a damaged level crossing.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.