Over-running engineering works: Utrecht-Amersfoort Schothorst (19 August 2024)
-
Disruption resolved Last update
Between Utrecht Centraal and Amersfoort Schothorst the train traffic is fully resumed.
- Show complete timeline…
-
Disruption reported
Between Utrecht Centraal and Amersfoort Schothorst fewer intercities are running due to over-running engineering works.
The extra travel time may be up to 15 minutes.
This will take until approximately 3:30 PM hours.Train measures
- Intercity 1700 Enschede/Den Haag C. - Den Haag C./Enschede is cancelled between Utrecht Centraal and Amersfoort Centraal
- Intercity 11700 Schothorst/Den Haag C. - Den Haag C./Schothorst is cancelled between Utrecht Centraal and Amersfoort Schothorst
- Speciale Trein 28300 Maliebaan/Utrecht C. - Utrecht C./Maliebaan is cancelled between Utrecht Centraal and Utrecht Maliebaan
Location of this disruption
This disruption is between Utrecht Centraal and Amersfoort Schothorst.
See the disruptions map for a live overview of all disruptions in the Netherlands.
More about this disruption
Statistics
This disruption started at 2:28 AM on August 19, 2024 and took 1 day, 22 hours, 48 minutes in total.
For statistics, this disruption is caused due to over-running engineering works.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.