Signalling and points failure: Breda-'s-Hertogenbosch (29 March 2024)
-
Disruption resolved Last update
Between Breda and 's-Hertogenbosch the train traffic is fully resumed.
-
Delays decreasing
Between Breda and 's-Hertogenbosch the restrictions are resolved.
Delays are decreasing.
Service is normal around 10:45 PM hours. -
Update
Between Breda and 's-Hertogenbosch no intercities are running due to a signalling and points failure.
Service is normal around 11:15 PM hours.Train measures
- Intercity 3600 Roosendaal/Zwolle - Zwolle/Roosendaal is cancelled between Breda and 's-Hertogenbosch
-
Update
Between Breda and 's-Hertogenbosch no intercities are running due to a signalling and points failure.
This will take until approximately 11:15 PM hours.Train measures
- Intercity 3600 Zwolle/Roosendaal - Roosendaal/Zwolle is cancelled between Breda and 's-Hertogenbosch
-
Update
Between Breda and 's-Hertogenbosch no intercities are running due to a signalling and points failure.
This will take until approximately 10:45 PM hours.Train measures
- Intercity 3600 Roosendaal/Zwolle - Zwolle/Roosendaal is cancelled between Breda and 's-Hertogenbosch
-
Update
Between Breda and 's-Hertogenbosch no intercities are running due to a signalling and points failure.
This will take until approximately 10:45 PM hours. -
Disruption
Between 's-Hertogenbosch and Tilburg no intercities are running due to a signalling and points failure.
This will take until approximately 10:45 PM hours.
More about this disruption
Statistics
This disruption started at 8:38 PM on March 29, 2024 and took 1 hour, 55 minutes in total.
For statistics, this disruption is caused due to a signalling and points failure.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.