technisch onderzoek

Technical investigation: Utrecht-'s-Hertogenbosch (18 March 2024)

  1. Disruption resolved Last update

    Between Geldermalsen and 's-Hertogenbosch the train traffic is fully resumed.

  2. Show complete timeline…
  3. Disruption reported

    Between Geldermalsen and 's-Hertogenbosch there are problems later today due to a technical investigation.
    Service is normal around 12:45 PM hours.

    Advice

    Between 12:15 PM and 12:45 PM, no trains will be running.

Location of this disruption

This disruption is between Geldermalsen and 's-Hertogenbosch.

Map of the location of this disruption

More about this disruption

Statistics

This disruption started at 11:55 AM on March 18, 2024 and took 1 hour, 49 minutes in total.

For statistics, this disruption is caused due to a technical investigation.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.