uitloop werkzaamheden

Over-running engineering works: Breda-Roosendaal (3 December 2022)

  1. Disruption resolved Last update

    Between Breda and Roosendaal the train traffic is fully resumed.

  2. Delays decreasing

    Between Breda and Roosendaal the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 11:30 AM hours.

  3. Update

    Between Breda and Roosendaal no trains are running due to over-running engineering works.
    The extra travel time is more than 60 minutes.
    This will take until approximately 11:30 AM hours.

    Train measures

    • Intercity 3600 Zwolle - Deventer - Nijmegen - Roosendaal is cancelled between Roosendaal and Breda
  4. Update

    Between Breda and Roosendaal no trains are running due to over-running engineering works.
    The extra travel time is more than 60 minutes.
    This will take until approximately 12:30 PM hours.

    Train measures

    • Intercity 3600 Zwolle - Deventer - Nijmegen - Roosendaal is cancelled between Roosendaal and Breda
  5. Update

    Between Breda and Roosendaal no trains are running due to over-running engineering works.
    The extra travel time is more than 60 minutes.
    This will take until approximately 12:00 PM hours.

    Train measures

    • Intercity 3600 Zwolle - Deventer - Nijmegen - Roosendaal is cancelled between Roosendaal and Breda
  6. Delays decreasing

    Between Breda and Roosendaal the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 11:30 AM hours.

  7. Delays decreasing

    Between Breda and Roosendaal the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 10:30 AM hours.

  8. Update

    Between Breda and Roosendaal no trains are running due to over-running engineering works.
    The extra travel time is more than 60 minutes.
    This will take until approximately 11:30 AM hours.

    Train measures

    • Intercity 3600 Zwolle - Deventer - Nijmegen - Roosendaal is cancelled between Roosendaal and Breda
  9. Delays decreasing

    Between Breda and Roosendaal the restrictions are resolved.
    Delays are decreasing.
    This will take until approximately 11:30 AM hours.

  10. Update

    Between Breda and Roosendaal no trains are running due to over-running engineering works.
    The extra travel time is more than 60 minutes.
    This will take until approximately 11:30 AM hours.

    Train measures

    • Intercity 3600 Zwolle - Deventer - Nijmegen - Roosendaal is cancelled between Roosendaal and Breda
  11. Update

    From and to Roosendaal far fewer trains are running due to over-running engineering works.
    The extra travel time is more than 60 minutes.
    This will take until approximately 10:00 AM hours.

    Train measures

    • Stoptrein 2500 Roosendaal - Antwerpen-C./Puurs keeps running normally between Roosendaal and Essen
    • Intercity 3600 Zwolle - Deventer - Nijmegen - Roosendaal is cancelled between Roosendaal and Breda
  12. Update

    From and to Roosendaal no trains are running due to over-running engineering works.
    The extra travel time is more than 60 minutes.
    This will take until approximately 10:00 AM hours.

    Train measures

    • Stoptrein 2500 Roosendaal - Antwerpen-C./Puurs is cancelled between Roosendaal and Essen
    • Intercity 3600 Zwolle - Deventer - Nijmegen - Roosendaal is cancelled between Roosendaal and Breda
  13. Update

    From and to Roosendaal no trains are running due to over-running engineering works.
    The extra travel time is more than 60 minutes.
    This will take until approximately 8:30 AM hours.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Bergen op Zoom and Rotterdam Centraal
    • Stoptrein 2500 Roosendaal - Antwerpen-C./Puurs is cancelled between Roosendaal and Essen
    • Intercity 3600 Zwolle - Deventer - Nijmegen - Roosendaal is cancelled between Roosendaal and Breda
    • Sprinter 5900 Dordrecht - Roosendaal is cancelled between Roosendaal and Oudenbosch
  14. Update

    From and to Roosendaal no trains are running due to over-running engineering works.
    The extra travel time is more than 60 minutes.
    This will take until approximately 8:30 AM hours.

  15. Disruption

    Between Lage Zwaluwe and Roosendaal there is a service disruption due to over-running engineering works.
    This will take until approximately 8:30 AM hours.

More about this disruption

Statistics

This disruption started at 6:59 AM on December 3, 2022 and took 4 hours, 24 minutes in total.

For statistics, this disruption is caused due to over-running engineering works.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights