uitloop werkzaamheden

Over-running engineering works: Amsterdam-Utrecht (12 September 2022)

  1. Disruption resolved Last update

    Between Amsterdam Centraal and Utrecht Centraal the train traffic is fully resumed.

  2. Delays decreasing

    Between Amsterdam Centraal and Utrecht Centraal the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 12:00 PM hours.

  3. Update

    Between Amsterdam Centraal and Utrecht Centraal fewer intercities are running due to over-running engineering works.
    The extra travel time may be up to 15 minutes.
    This will take until approximately 12:00 PM hours.

    Train measures

    • Intercity 3900 Enkhuizen - Utrecht C. - Eindhoven C. - Heerlen is cancelled between Amsterdam Centraal and Eindhoven Centraal
  4. Update

    Between Amsterdam Centraal and Utrecht Centraal fewer intercities are running due to over-running engineering works.
    The extra travel time may be up to 15 minutes.
    This will take at least until 12:00 PM hours.

    Train measures

    • Intercity 3900 Enkhuizen - Utrecht C. - Eindhoven C. - Heerlen is cancelled between Amsterdam Centraal and Eindhoven Centraal
  5. Update

    Between Amsterdam Centraal and Utrecht Centraal fewer intercities are running due to over-running engineering works.
    The extra travel time may be up to 15 minutes.
    This will take until approximately 10:30 AM hours.

    Train measures

    • Intercity 3900 Enkhuizen - Utrecht C. - Eindhoven C. - Heerlen is cancelled between Amsterdam Centraal and Eindhoven Centraal
  6. Update

    Between Amsterdam Centraal and Utrecht Centraal fewer intercities are running due to over-running engineering works.
    The extra travel time may be up to 15 minutes.
    This will take until approximately 10:00 AM hours.

    Train measures

    • Intercity 3900 Enkhuizen - Utrecht C. - Eindhoven C. - Heerlen is cancelled between Amsterdam Centraal and Eindhoven Centraal
  7. Disruption

    Between Amsterdam Centraal and Utrecht Centraal fewer intercities are running due to over-running engineering works.
    The extra travel time may be up to 15 minutes.
    This will take until approximately 8:30 AM hours.

    Train measures

    • Intercity 3900 Enkhuizen - Utrecht C. - Eindhoven C. - Heerlen is cancelled between Amsterdam Centraal and Eindhoven Centraal

More about this disruption

Statistics

This disruption started at 6:42 AM on September 12, 2022 and took 5 hours, 16 minutes in total.

For statistics, this disruption is caused due to over-running engineering works.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS and NS International.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights